South Carolina impact fees by county

As of Nov 9, 2026, Groundwork has the published fee schedule for 3 jurisdictions in South Carolina, each from the jurisdiction's own document. South Carolina counties and cities may charge development impact fees under the South Carolina Development Impact Fee Act (S.C. Code 6-1-910 and following). Water and sewer utilities charge their own impact or capacity fees when a new home connects.

Fees on one new single-family home

Status on Nov 9, 2026. A per-square-foot tax is shown with its total for a 2,000 sq ft home.

Who charges itOne new homeDateSource
Charleston Water System service areaWater and sewer impact fees$11,290Since Jan 1, 2026Source
Greenville Water service area (water only)Water capacity fee$1,390–$2,780 by unit sizeSince Jan 1, 2026Source
Horry CountyImpact fee$995–$3,104 by home sizeAdopted Jul 14, 2026Source

A county or city not named on this page is not tracked yet, which does not mean it charges nothing.

What each figure covers

The law

South Carolina counties and cities may charge development impact fees under the South Carolina Development Impact Fee Act (S.C. Code 6-1-910 and following). Water and sewer utilities charge their own impact or capacity fees when a new home connects. S.C. Code Title 6 Chapter 1.

Every figure is the jurisdiction's own published schedule, linked in its row; confirm with the jurisdiction before you rely on it. Florida: Florida impact fees by county.

Questions

Does South Carolina charge impact fees on a new home?

South Carolina counties and cities may charge development impact fees under the South Carolina Development Impact Fee Act (S.C. Code 6-1-910 and following). Water and sewer utilities charge their own impact or capacity fees when a new home connects. Whether a home pays, and how much, depends on the county, city or utility; the table lists each schedule Groundwork has checked.

Do I pay these fees when I buy vacant land?

No. They are due while a new home is built: at the building permit in most places, before the certificate of occupancy in some, and a utility fee when the home connects to water and sewer. They belong in the cost of building, not the land price.

Does a county missing from the table charge nothing?

Not necessarily. A county or city that is not listed has not been checked yet; ask its building or planning department.